An Act to Reinstate and Extend the Deadline for Commencement of Construction of a Hydroelectric Project Involving the Gibson Dam.
An Act to Reinstate and Extend the Deadline for Commencement of Construction of a Hydroelectric Project Involving the Gibson Dam.
- [2] pages ; 24 cm
Shipping list no.: 2019-0096-P. "July 27, 2018 (S. 490)." "132 Stat. 1556." "Public Law 115-219." CRDP Program record.
Hydroelectric power plants--Law and legislation--Montana.
Hydroelectric power plants--Licenses--Montana.
Statutes and codes.
0575
AE 2.110:115-219
Public Law 115-219
Shipping list no.: 2019-0096-P. "July 27, 2018 (S. 490)." "132 Stat. 1556." "Public Law 115-219." CRDP Program record.
Hydroelectric power plants--Law and legislation--Montana.
Hydroelectric power plants--Licenses--Montana.
Statutes and codes.
0575
AE 2.110:115-219
Public Law 115-219